Hospital Expansion Project Timeline

Construction Timeline

  • Parking Lot Demolition - April 3, 2019
  • House Demolition (Central and Harrison) - March 26 2019
  • Ground Breaking - May 21st 2019
  • Start Construction of Addition - June 2019
  • Substantial Completion - November 2020
  • See First Patient in New Addition - February 2021
  • Renovation of Existing Hospital Space - March 2021
  • Total Project Completion - April 2021